Project update #13
Hi,
This update will be a shorter one. Over the past two weeks, we’ve primarily focused on quality control and testing, as we received a large number of samples from our suppliers.
Progress on Standard Parts
Last week, we placed orders for nearly all standard components, including motors, microcontrollers, screens, and more. Since we were able to test samples in advance, we’re confident in these selections. While some parts are still being refined, the core components remain unchanged, meaning that once everything is ready for assembly, we won’t have to wait for supplier lead times.
Outer Shell Design
We’ve also made significant progress on the outer shell. Currently, some samples are in production with one of our suppliers. We decided to replace plastic panels with sheet metal to improve durability, reduce shipping damage, and minimize electromagnetic interference. We expect to receive the first samples next week, which will allow us to begin the design iteration process for these parts.
Ahead of Schedule!
Even though this update may seem smaller, we’re excited to share that we are currently ahead of schedule! Of course, timelines can shift, and the main challenge we anticipate is the certification process. However, being able to place major component orders just six weeks after the campaign ended is a significant milestone for us.
We’ll keep you updated as we continue making progress!
The Closed Loop Makers Team